Materials Management Plans (MMPs): Reusing Excavated Soil Without It Being Waste

21 October 2026 · 9 min read · Written by the VerdCore team · Reviewed by Franklyn Mbama-chris, MBA

A Materials Management Plan is not a waste plan. It is the document that stops your excavated soil being waste in the first place — and with the lower rate of landfill tax having more than doubled in April 2026, it is the difference between reusing material and paying to bury it.

What a Materials Management Plan actually does

Dig soil out of the ground and move it, and the default legal position is that you are now holding waste. That triggers the whole regime: duty of care, carriers, transfer notes, permits, gate fees and landfill tax — for material that may be perfectly clean and that you would happily put back thirty metres away.

A Materials Management Plan (MMP) is the document that rebuts that default. It is prepared under the CL:AIRE Definition of Waste: Development Industry Code of Practice — universally shortened to the DoWCoP — a voluntary framework recognised by the Environment Agency and Natural Resources Wales. Follow it properly and the excavated material is treated as a product being used for a purpose, not as waste being disposed of.

That is the entire point of the exercise, and it is worth being precise about it, because the name misleads people. An MMP is not a waste plan. A Site Waste Management Plan governs the material that is waste. An MMP governs the material you have kept out of that category. A large earthworks project normally needs both, covering different piles of the same site.

The four tests the material has to pass

The Code is not a formality you can complete after the fact. Material only falls outside the waste definition if you can show all four of the following, and the Plan exists to evidence them:

  1. Suitability for use. The material is chemically and geotechnically suitable for the specific purpose it is going into, judged against a risk assessment for that receptor — not suitable in general.
  2. Certainty of use. There is a defined, designed use for it. "We will find somewhere for it" is a stockpile of waste, whichever way it is described.
  3. Quantity. Only the quantity actually needed for the designed use. Surplus beyond the design is not covered.
  4. No unacceptable risk. Using it poses no unacceptable risk to human health or the environment, with any treatment limited to what the Code permits.

Fail any one of them and the material is waste again, retrospectively — which is why the Plan has to exist before the excavator starts, not after.

The three scenarios

The DoWCoP covers three distinct situations, and which one you are in changes what you have to evidence:

Scenario What it covers
Site of origin Material excavated and reused on the same site it came from, contaminated or not. The most common case by a wide margin.
Direct transfer Clean, naturally occurring soil moved straight from one site to another and reused without treatment.
Cluster Material from a defined group of sites, treated at a shared fixed or mobile facility and redistributed within the group.

Site of origin is the one most projects use, and it is also the one where the paperwork is most often skipped, because it feels like nothing is leaving the red line. The regime does not care: material that has been excavated has been discarded unless the Code says otherwise.

What goes in the Plan

The Plan has to be specific enough that someone auditing it two years later can tell whether what happened matches what was proposed. In practice that means:

CL:AIRE publishes templates, and using them is the sensible default — a Plan in an unfamiliar format gives a Qualified Person more reason to send it back.

The Qualified Person and the Declaration

The Plan does not take effect because you wrote it. It takes effect because a Qualified Person (QP) — an independent competent professional on CL:AIRE's QP Register — reviews it and signs a Declaration confirming it meets the Code. The Declaration is submitted through CL:AIRE, with a fee, before the material is used.

Three things about the QP catch projects out:

Afterwards, a verification report records what was actually placed against what the Plan proposed. It is not usually submitted anywhere by default, but the Environment Agency can ask for it on audit, and a project that cannot produce one has in practice lost its Code defence.

What it is worth — the money

The alternatives to an MMP are an environmental permit, a registered waste exemption with its volume caps, or paying to dispose. The third is the one the numbers are measured against.

From 1 April 2026 the rates are £130.75 per tonne at the standard rate and £8.65 per tonne at the lower rate. The lower rate matters more than it used to: it was £4.05 a tonne the year before, so it more than doubled in a single step, and the gap that used to make soil disposal a rounding error has closed.

On 5,000 tonnes of excavated material — a modest figure for a commercial scheme with a basement — the landfill tax alone is:

Tax on 5,000 t
Naturally occurring soil qualifying for the lower rate £43,250
Material attracting the standard rate £653,750

And that is tax only. It sits on top of gate fees, haulage out, and the cost of buying and carting in replacement fill to backfill the hole you have just created. Note also that contaminated soil generally does not qualify for the lower rate — so the material you are most tempted to send away is the material that costs the most to send.

What it is worth — the carbon

The carbon case is usually made loosely. It is worth doing properly, because the result is not where people expect.

Take the same 5,000 tonnes. Assume 20-tonne loads, so 250 loads out — and, because the hole still has to be filled, 250 loads of imported fill back in. At a 30-mile round trip per load that is 15,000 HGV vehicle-miles.

kgCO₂e
5,000 t of soil to landfill 97,768.8
The same 5,000 t reused instead 5,069.9
Avoided by keeping it on site 92,698.9
Avoided haulage (15,000 HGV vehicle-miles) 20,423.9
Total avoided 113,122.8

That is 113.1 tCO₂e — on one earthworks decision. For scale, the entire quarter of site activity in our worked contractor example, covering all plant fuel, all materials and all deliveries, came to 196.8 tCO₂e.

Two honest caveats on those figures. The disposal factor for soil is low per tonne — 19.55 kgCO₂e/t to landfill against 1.01 reused — so this is a volume effect, not a high-intensity one; the number is large because the tonnage is. And the haulage line depends entirely on the round-trip distance you assume, which is a real number on a real project and should be used instead of ours. The factors are the DEFRA/DESNZ set for the reporting year, the same ones behind our emission factor work.

Common mistakes

Where it sits alongside everything else

An MMP is one of three documents that between them govern what happens to material on a construction site, and they are routinely confused:

Document Governs
Materials Management Plan Excavated material reused as a product, outside the waste regime
Site Waste Management Plan Material that is waste — forecast, segregation, carriers, disposal
Environmental Management Plan The controls around the works themselves — dust, water, noise, ecology

They also connect upward. Material reused on site is a Scope 3 reduction you can actually evidence, which is the kind of specific, quantified measure a Carbon Reduction Plan needs and most of them lack. And the principal designer's duty to design out risk under CDM 2015 includes designing an earthworks balance that does not need a thousand lorry movements in the first place — the cheapest load is the one that never leaves.

Frequently asked questions

What is a Materials Management Plan?
A Materials Management Plan is the document required under the CL:AIRE Definition of Waste Development Industry Code of Practice that sets out what excavated material a project will produce, where each parcel will be reused, and the evidence that it is suitable for that use. Where it is followed, the material is treated as a product rather than as waste.
Is a Materials Management Plan a legal requirement?
No. The Code of Practice is voluntary. What it provides is a route recognised by the Environment Agency to demonstrate that excavated material is not waste. The alternatives are an environmental permit, a registered waste exemption, or handling the material as waste and paying to dispose of it.
Who is the Qualified Person?
An independent competent professional on CL:AIRE's Qualified Person Register who reviews the Materials Management Plan and signs the Declaration confirming it meets the Code. They must not have written the plan they are reviewing, and the Declaration is submitted through CL:AIRE before the material is used.
What is the difference between an MMP and a Site Waste Management Plan?
A Site Waste Management Plan governs material that is waste — how it is segregated, carried and disposed of. A Materials Management Plan governs material that is not waste, because it is being reused under the Code of Practice. Most earthworks projects need both, covering different material.
How much does an MMP save?
It avoids landfill tax, disposal gate fees, haulage out and the cost of importing replacement fill. From 1 April 2026 the standard rate of landfill tax is £130.75 per tonne and the lower rate £8.65 per tonne, so on a scheme moving thousands of tonnes the saving is usually measured in hundreds of thousands of pounds.
What are the three DoWCoP scenarios?
Reuse on the site of origin, direct transfer of clean naturally occurring soil between sites without treatment, and reuse within a defined Cluster project where material from several sites is treated at a shared facility.

Keep the materials record with the rest of the project